PM opens Moghbazar-Mouchak flyover for traffic


PM opens Moghbazar-Mouchak flyover for traffic

Prime Minister Sheikh Hasina on Thursday (Oct 26) opened the Kakrail-Malibagh, Rajarbagh-Mouchak, Rampura-Mouchak and Mouchak-Eskaton portions of the much-awaited Moghbazar-Mouchak Flyover. She inaugurated the flyover through a videoconference at noon.

With the inauguration of the rest 5.5-km overpass of the entire 8.7-km one, vehicles can now go over eight road intersections and three level-crossings at Karwan Bazar, Moghbazar and Malibagh, substantially improving the city trips.

Aiming to ease traffic in one of the city's busiest areas, the construction work on the integrated Moghbazar-Mouchak Flyover Project began in January 2013 with a deadline to complete it by June 2015.

On Jan 19, 2016, the project timeframe has been extended by another 18 months till June 2017 as its length has been extended through redesigning of its structure to make it more usable for easing traffic jam in the capital. However, the construction farm also missed the deadline.

On March 30 last year, Prime Minister Sheikh Hasina inaugurated the first part, stretching over two kilometres from Holy Family Hospital to Saatrasta intersection.

Local Government Minister Khandker Mosharraf Hossain inaugurated the one-km portion, Eskaton to Moghbazar Wireless Gate, on Sep 15, 2016 and the 450-meter long part, Hatirjheel to Sonargaon intersection, on May 17 this year.